Office of Hearings and Mediation Services
Docket Management System
Overview - 202175746
|
|
Case Name: |
Hecate Energy Cider Solar LLC |
Program ID Number(s): |
View |
|
Region: |
Region 8 |
Case Type: |
NYS Office of Renewable Energy Siting
|
DEC Office: |
N/A |
DEC Program Type(s): |
View |
Statutes/Regulations: |
View |
SEQR Class: |
|
SEQR Info: |
View |
Location Address: |
View |
Status: |
Decision Issued |
City/Town & County: |
ELBA, TOWN OF (GENESEE COUNTY) (GENESEE)
|
Decision Document:
|
|
ALJ Assigned: |
Oconnell |
|
Referral Date: |
6/4/2021 |
Overview:
Executive Law ยง 94-c renewable energy power plant siting proceeding. Applicant proposes to construct a 500 MW solar energy generation facility in the Towns of Elba and East Oakfield, Genesee County. Section 94-c application filed 6/3/21. Notice of incomplete application issued 8/2/21. In person public comment hearing scheduled for May 10, 2022 at 5:00 pm in Elba, New York.
|
|