Agreement.BCP.C224268.2018-03-20.Executed BCA Site No. C224268, 34 Berry Street.pdf 635K
Certificate of Completion.BCP.C224268.2022-12-02.Executed COC.pdf 956K
Decision Document.BCP.C224268.2021-02-09.Decision Document.pdf 1.3M
Easement.BCP.C224268.2022-10-06.Environmental Easement (Recorded).pdf 530K
Fact Sheet.BCP.C224268.2020-07-03.Fact Sheet #1 RAWP comment period.pdf 292K
Fact Sheet.BCP.C224268.2020-09-22.Factsheet #1 RAWP Comment period extended.pdf 292K
Fact Sheet.BCP.C224268.2021-02-22.Factsheet #2 Announcing RA start.pdf 293K
Fact Sheet.BCP.C224268.2022-07-29.Fact Sheet #3 RA Complete.pdf 1.2M
Fact Sheet.BCP.C224268.2022-12-08.Factsheet #4 COC released.pdf 879K
Report.BCP.C224268.2019-11-12.Final RIR.pdf 92M
Report.BCP.C224268.2021-01-20.RIR Addendum with Certification.pdf 183M
Report.BCP.C224268.2022-11-03.Final FER.pdf 424M
Work Plan.BCP.C224268.2018-07-09.Appendix C Final RIWP.pdf 230M
Work Plan.BCP.C224268.2018-07-09.Final RIWP.pdf 20M
Work Plan.BCP.C224268.2018-07-10.Citizen Participation Plan.pdf 587K
Work Plan.BCP.C224268.2019-03-19.Final approved IRMWP.pdf 11M
Work Plan.BCP.C224268.2020-12-10.Final Certified In-Situ Design Document.pdf 70M
Work Plan.BCP.C224268.2021-02-08.Final Certified RAWP.pdf 6.7M
Work Plan.BCP.C224268.2021-02-08.Final RAWP Appendix C Previous Env Reports.pdf 398M
Work Plan.BCP.C224268.2025-02-03.The Revised SMP [Final].pdf 34M