Index of /data/DecDocs/C241192
Name Size
Agreement.BCP.C241192.2017-03-27.Halletts Point, Buildings 2 and 3.pdf 1.5M
Agreement.BCP.C241192.2024-10-10.Amendment No1 Multiple Changes.pdf 4.3M
Application.BCP.C241192.2008-10-22.Phase 2 Report - Famitech.pdf 28M
Application.BCP.C241192.2008-10-22.Phase I Report - Famitech.pdf 76M
Application.BCP.C241192.2012-10-15.Phase I Update Report - Famitech.pdf 86M
Application.BCP.C241192.2014-09-19.Phase I Report for 2602-2640 1st Street - Famitech.pdf 196M
Application.BCP.C241192.2015-02-02.Appendix B-1 - Remedial Investigation Report.pdf 11M
Application.BCP.C241192.2016-10-03.Appendix D2 and D3.pdf 2.1M
Application.BCP.C241192.2016-10-03.Sanborn Maps.pdf 2.2M
Application.BCP.C241192.2016-11-22.Complete BCP Application.pdf 57M
Decision Document.BCP.C241192.2017-10-27.DD.pdf 1.0M
Easement.BCP.C241192.2024-11-20.Recorded EE.pdf 636K
Easement.BCP.C241192.2024-11-22.Notice to Municipality.pdf 5.1M
Fact Sheet.BCP.C241192.2017-03-27.FS#1 RIWP comment period ENGLISH.pdf 138K
Fact Sheet.BCP.C241192.2017-03-27.FS#1 RIWP comment period SPANISH.pdf 160K
Fact Sheet.BCP.C241192.2017-08-23.FS#2 RAWP comment period SPANISH.pdf 254K
Fact Sheet.BCP.C241192.2017-08-23.FS#2_RAWP_comment_period_ENGLISH.pdf 287K
Fact Sheet.BCP.C241192.2024-12-17.FER_FINAL_ENGLISH.pdf 765K
Fact Sheet.BCP.C241192.2024-12-17.FER_FINAL_SPANISH.pdf 735K
Fact Sheet.BCP.C241192.2025-01-06.COC_FINAL_ENGLISH.pdf 726K
Fact Sheet.BCP.C241192.2025-01-06.COC_FINAL_SPANISH.pdf 701K
Report.BCP.C241192.2017-07-14.RIR.pdf 1.6G
Report.BCP.C241192.2024-12-24.FER_Appendix_A-M.pdf 553M
Report.BCP.C241192.2024-12-24.FER_Appendix_J3.pdf 1.3G
Report.BCP.C241192.2024-12-24.FER_Appendix_K.pdf 3.3M
Report.BCP.C241192.2024-12-24.FER_Appendix_L.pdf 96M
Report.BCP.C241192.2024-12-24.FER_Text_Tables_Figures.pdf 25M
Work Plan.BCP.C241192.2017-03-24.CP plan.pdf 1.9M
Work Plan.BCP.C241192.2017-06-02.RIWP.pdf 282M
Work Plan.BCP.C241192.2017-06-30.IRMWP.pdf 17M
Work Plan.BCP.C241192.2017-10-16.FINAL_RAWP.pdf 1.4G
Work Plan.BCP.C241192.2021-02-18.Minor RAWP Modification.pdf 4.3M
Work Plan.BCP.C241192.2022-11-14.Endpoint Sampling Plan.pdf 23M
Work Plan.BCP.C241192.2024-12-18.SMP Final.pdf 41M