File listing

Files for this location:

NameSize
Agreement.BCP.C241219.2018-11-30.Executed BCA.pdf9.6M
Agreement.BCP.C241219.2025-07-24.BCA Amendment No. 1_TPC.pdf3.1M
Application.BCP.C241219.1990-01-04.Appendix B_ Site Investigation Proposal.pdf2.1M
Application.BCP.C241219.1990-02-14.Appendix B_ Hazardous Substances Survey and Report.pdf 75M
Application.BCP.C241219.1990-07-10.Appendix B_ Gasoline Tank Removal Affidavit & Receipts.pdf686K
Application.BCP.C241219.2003-01-01.Appendix B_ 2003 Site Plan.pdf143K
Application.BCP.C241219.2003-03-28.Appendix B_ Level 2 ESA - ATC Associates.pdf5.7M
Application.BCP.C241219.2003-07-03.Appendix B_ PBS Document and Tank Testing Documents.pdf1.2M
Application.BCP.C241219.2005-10-10.Appendix B_ 7500gal Heating Oil Tank Abandonment Documents.pdf2.2M
Application.BCP.C241219.2007-02-06.Appendix B_ 2003-2007 Waste Oil and 7500gal Heating Oil Tank Pump-Out Receipts.pdf711K
Application.BCP.C241219.2008-07-18.Appendix B_ PBS Documents.pdf1.6M
Application.BCP.C241219.2009-03-31.Appendix B_ NOV & Order on Consent.pdf1.0M
Application.BCP.C241219.2009-05-04.Appendix B_ Waste Oil Tank Abandonment Receipts & Invoice.pdf305K
Application.BCP.C241219.2009-05-20.Appendix B_ Waste Oil Tank Registration & Sampling Results .pdf648K
Application.BCP.C241219.2009-07-21.Appendix B_ Tank Abandonment Affidavit.pdf 94K
Application.BCP.C241219.2018-08-29.Complete BCP Application.pdf 30M
Certificate of Completion.BCP.C241219.2026-09-28.Certificate of Completion- Revised.pdf3.1M
Decision Document.BCP.C241219.2024-09-30.27-10 49th Ave DD.pdf2.0M
Easement.BCP.C241219.2026-06-10.Recorded EE Amendment.pdf364K
Fact Sheet.BCP.C241219.2019-04-12.IRM Fact Sheet .pdf212K
Fact Sheet.BCP.C241219.2024-02-01.RAWP Fact Sheet.pdf1.0M
Fact Sheet.BCP.C241219.2025-10-28.Construction Complete_FER Factsheet.pdf1.2M
Fact Sheet.BCP.C241219.2025-12-10.COC Issuance Factsheet.pdf772K
Report.BCP.C241219.2017-11-01.Phase I Environmental Site Assessment.pdf 47M
Report.BCP.C241219.2018-03-01.Remedial Investigation Report.pdf 77M
Report.BCP.C241219.2019-01-31.Remedial Investigation Report.pdf 17M
Report.BCP.C241219.2021-12-21.December 2021 Interim Remedial Measures Construction Completion Report.pdf 57M
Report.BCP.C241219.2023-08-15.SVES Expansion Pilot Test Report.pdf2.2M
Report.BCP.C241219.2024-06-11.PAH GW Results Summary Letter.pdf8.9M
Report.BCP.C241219.2025-11-14.Final Engineering Report.pdf169M
Work Plan.BCP.C241219.2019-01-01.IRM WP.pdf 55M
Work Plan.BCP.C241219.2024-05-14.Revised PAH GW Sampling Plan.pdf2.3M
Work Plan.BCP.C241219.2024-09-30.August 2024 RAWP.pdf 21M
Work Plan.BCP.C241219.2025-02-24.Revised February 2025 SVIWP.pdf1.4M
Work Plan.BCP.C241219.2025-10-28.Citizen Participation Plan_updated.pdf1.0M
Work Plan.BCP.C241219.2026-10-08.Site Management Plan_rev1.pdf 61M