Agreement.BCP.C241213.2018-10-16.DOT Relocation Site.pdf6.6M
Agreement.BCP.C241213.2021-11-01.Executed BCA Amendment No. 1 -Add 1 Party .pdf 12M
Agreement.BCP.C241213.2022-01-28.Executed BCA Amendment No. 2 - Transfer Title .pdf2.8M
Application.BCP.C241213.2013-08-26.Phase 1 Environmental Site Assessment - Ecosystems Strategies Inc..pdf 73M
Application.BCP.C241213.2017-07-01.Subsurface Phase 2 Site Investigation - AKRF.pdf6.5M
Application.BCP.C241213.2017-07-26.Phase 1 Environmental Site Assessment - AKRF.pdf 31M
Application.BCP.C241213.2018-04-25.Attachment C - Previous Environmental Reports.pdf 37M
Application.BCP.C241213.2018-05-29.Complete Application.pdf 28M
Report.BCP.C241213.2019-03-29.RIWP 022519.pdf 47M
Report.BCP.C241213.2019-05-28.Citizen Participation Plan_DOT Relocation_C241213.pdf1.0M
Report.BCP.C241213.2020-04-09.C241213_DOT Relocation_Remedial Investigation Report_Final.pdf727M
Report.BCP.C241213.2021-02-23.DRAFT.C241213.RAWP.DOTRelocation.pdf486M
Report.BCP.C241213.2024-07-10.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2024-08-12.Monthly Progress Report.pdf 38K
Report.BCP.C241213.2024-09-10.Monthly Progress Report.pdf 38K
Report.BCP.C241213.2024-10-10.Monthly Progress Report.pdf 38K
Report.BCP.C241213.2024-11-11.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2024-12-10.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2025-01-10.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2025-02-10.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2025-03-10.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2025-04-10.Monthly Progress Report.pdf 39K
Report.BCP.C241213.2025-05-12.Monthly Progress Report.pdf 36K
Report.BCP.C241213.2025-06-10.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2025-07-10.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2025-08-11.Monthly Progress Report.pdf 38K
Report.BCP.C241213.2025-09-10.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2025-10-10.Monthly Progress Report.pdf 38K
Report.BCP.C241213.2025-11-10.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2025-12-10.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2026-01-12.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2026-02-11.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2026-03-10.Monthly Progress Report.pdf 39K
Report.BCP.C241213.2026-04-10.Monthly Progress Report.pdf 39K
Report.BCP.C241213.2026-05-11.Monthly Progress Report.pdf 37K
Report.BCP.C241213.2026-06-10.Monthly Progress Report.pdf 37K
Work Plan.BCP.C241213.2021-07-07.C241213.RAWP.DOTRelocation.Final.pdf491M