Index of /data/DecDocs/C241259
Name Size
Work Plan.BCP.C241259.2021-12-03.Remedial Investigation Work Plan (RIWP) .pdf 73M
Work Plan.BCP.C241259.2023-03-09.RAWP Appendices A - C.pdf 72M
Application.BCP.C241259.2021-07-20.Draft Remedial Investigation Work Plan.pdf 71M
Report.BCP.C241259.2022-08-19.Remedial Investigation Report (RIR).pdf 46M
Application.BCP.C241259.1994-06-09.Evaluation of Existing Parking Lot Fill.pdf 41M
Application.BCP.C241259.2021-07-18.Complete Application.pdf 39M
Work Plan.BCP.C241259.2022-09-15.Draft Remedial Action Work Plan (RAWP).pdf 39M
Work Plan.BCP.C241259.2023-03-09.Remedial Action Work Plan (RAWP).pdf 38M
Work Plan.BCP.C241259.2023-03-09.RAWP Appendices D - H.pdf 28M
Application.BCP.C241259.2012-03-06.Supplemental Phase II Environmental Site Assessment.pdf 8.4M
Agreement.BCP.C241259.2022-09-30.Amendment No. 1.pdf 6.6M
Application.BCP.C241259.2003-04-30.Phase I Environmental Site Assessment.pdf 2.6M
Application.BCP.C241259.2004-03-05.Phase II Environmental Site Assessment.pdf 2.0M
Fact Sheet.BCP.C241259.2022-09-14.Factsheet RI Report - Hindi.pdf 1.5M
Fact Sheet.BCP.C241259.2022-09-14.Factsheet RI Report.pdf 1.5M
Fact Sheet.BCP.C241259.2022-12-07.Factsheet RAWP -45-Day Commnts. Chinise.pdf 1.4M
Fact Sheet.BCP.C241259.2022-09-14.Factsheet RI Report - Chinese.pdf 1.4M
Fact Sheet.BCP.C241259.2022-12-07.Factsheet. RAWP - 45-Day Commnts Period.pdf 1.3M
Fact Sheet.BCP.C241259.2022-12-07.Factsheet RAWP 45-Day ublic Commnts Hindi.pdf 1.2M
Agreement.BCP.C241259.2021-12-03.Executed BCA.pdf 1.1M
Work Plan.BCP.C241259.2022-01-12.Citizen Participation Plan (CPP).pdf 941K
Decision Document.BCP.C241259.2023-03-16.Decision Document.pdf 307K