Name
Size
Application.HW.442027.2019-03-29.OU01 REF Project - NOIA Response 1.pdf
17M
Consent Order.HW.442027.1998-02-24.A4-0345-96-07.BASF_Main_Plant.pdf
3.5M
Consent Order.HW.442027.2003-10-10.A4-0490-0703.RD-RA_order-OU1.pdf
3.8M
Consent Order.HW.442027.2005-04-21.BASF_order_on_consent.pdf
1.1M
Consent Order.HW.442027.2013-11-06.signed_NRD-order_between_BASF_and_DEC.pdf
9.3M
Consent Order.HW.442027.2017-02-15.SSF OU2 RD RA Consent Order.pdf
342K
Consent Order.HW.442027.2017-02-23.OU2 RD RA Executed Order with Cover Letter 2-23-17.pdf
4.3M
Decision Document.HW.442027.2010-05-21.ESD_OU1-lagoon alternative cap.pdf
1.8M
Easement.HW.442027.2013-11-18.BASF OU1 Deed Restriction filed.pdf
642K
Easement.HW.442027.2013-11-18.OU1 Deed_Restriction-recorded.pdf
642K
Fact Sheet.HW.442027.2002-04-01.RI_available - OU1.pdf
18K
Fact Sheet.HW.442027.2002-05-01.fact sheet for IRM excavations at OU1.pdf
17K
Fact Sheet.HW.442027.2002-10-01.OU1 IRM soil_SVE_system.pdf
17K
Fact Sheet.HW.442027.2003-02-01.RA proposed for OU01 BASF Manufacturing Plant Site.pdf
553K
Fact Sheet.HW.442027.2003-04-01.OU1 sludge_excav_start.pdf
17K
Fact Sheet.HW.442027.2003-07-01.OU1 IRM Modification for BASF.pdf
174K
Fact Sheet.HW.442027.2009-09-01.OU1 and OU2 NYSDEC_pilot-sediment-treatment.pdf
1.2M
Fact Sheet.HW.442027.2016-02-11.Fact Sheet announcing release of OU2 PRAP.pdf
3.0M
Fact Sheet.HW.442027.2018-06-06.BASF OU02 Remedial Action Start - SSF Dredging Project.pdf
1.6M
Fact Sheet.HW.442027.2019-07-12.OU2 2019 Dredging to Commence.pdf
513K
PRAP.HW.442027.2003-02-12.basf_mfg_plant_OU1.pdf
10M
PRAP.HW.442027.2016-02-11.BASF OU 02 PRAP.pdf
3.6M
Report.HW.442027.2000-11-13.RI_and_Supplemental_RI.pdf
93M
Report.HW.442027.2001-08-01.23.Add_RI_Activities_Vol_one.pdf
25M
Report.HW.442027.2001-08-03.Add_RI_Activities_Vol_two.pdf
12M
Report.HW.442027.2001-11-26.OU1 FS Report.pdf
56M
Report.HW.442027.2002-07-19.Lagoon Soil Characterization Sampling from ROUX Assoc.pdf
467K
Report.HW.442027.2004-08-03.lagoon-closure_sampling-analysisQAPP.pdf
16M
Report.HW.442027.2004-08-23.Off_Site_Investigation_for_Soil_Gas_and_Groundwater.pdf
55M
Report.HW.442027.2004-08-23.OU2_Investigation_SoilGas_AppC.pdf
25M
Report.HW.442027.2004-08-23.OU2_Investigation_SoilGas_thru_AppB.pdf
11M
Report.HW.442027.2004-08-27.OU2_Investigation_HudsonRiver-sediment.pdf
4.7M
Report.HW.442027.2005-12-16.ROUX IRMRAC - Appendix C OU1 Soil Disposal Manifests.pdf
35M
Report.HW.442027.2005-12-16.ROUX IRMRAC - Appendix D OU1 Soil HazWaste Manifests.pdf
108M
Report.HW.442027.2005-12-16.ROUX IRMRAC - Appendix E OU1 Groundwater Manifests.pdf
24M
Report.HW.442027.2005-12-16.Roux_IRM_RAC - OU1 Soil Removals.pdf
18M
Report.HW.442027.2007-06-01.HR_OU2_Invest_Appendix_D-Part_1 - Sediment and SW Data.pdf
211K
Report.HW.442027.2007-06-01.HR_OU2_Invest_Appendix_D-Part_2 - DUSRs.pdf
63M
Report.HW.442027.2007-06-01.HR_OU2_Invest_Appendix_F - Sediment Boring Logs.pdf
2.3M
Report.HW.442027.2007-06-01.HR_OU2_Invest_Appendix_G - Statistical Analyses.pdf
742K
Report.HW.442027.2007-06-01.Hudson-River_OU2_Investigation - Sediment and SW.pdf
16M
Report.HW.442027.2008-10-29.SAV_survey-Outfall_Construction.Empire.pdf
4.2M
Report.HW.442027.2009-01-01.HR_OU2_Investigation_Appendix_C - Sediment and PoreWater Data and DUSRs.pdf
20M
Report.HW.442027.2009-01-01.HR_OU2_Investigation_Appendix_F - Sediment Toxicity Study.pdf
25M
Report.HW.442027.2009-01-01.HR_OU2_Investigation_Appendix_I - Sressor Response Study.pdf
2.4M
Report.HW.442027.2009-01-01.Hudson-River_OU2_Investigation - Minus Separate Appendices.pdf
29M
Report.HW.442027.2009-01-22.Analytical_of_Lagoon_common_fill.pdf
1.2M
Report.HW.442027.2009-03-31.pcbs-in-Hudson-River_Sediment - OU2 Data Eval.pdf
5.0M
Report.HW.442027.2010-07-19.Focused Feasibility Study for OU01 Lagoon GW.pdf
3.9M
Report.HW.442027.2010-07-30.OU2_HRSediment-Nature_and_Extent-summary.pdf
20M
Report.HW.442027.2010-12-17.BASF Smokestack Evaluation by RyanBiggs - OU1 Demolition Work.pdf
362K
Report.HW.442027.2011-04-15.Lagoon_Area_GW-Dec2010_results.pdf
520K
Report.HW.442027.2011-05-20.dredged_sediment_treatment_pilot_study - OU1 Main and Lagoon and OU2 Dredging.pdf
6.2M
Report.HW.442027.2011-05-20.dredged_spoil-data_packet OU1 Main and Lagoon and OU2 Dredging.pdf
56M
Report.HW.442027.2012-07-12.GW Performance Monitoring Report.pdf
102M
Report.HW.442027.2012-07-25.BASF PCB in Hudson River Report.pdf
5.4M
Report.HW.442027.2013-01-31.OU2_Dredged_Sediment_Treatment_Pilot_Study_Closure_Rpt.pdf
23M
Report.HW.442027.2013-02-01.Southern FS Study Sediment Data Rpt - Appendix A - Lab Reports.pdf
122M
Report.HW.442027.2013-02-01.Southern FS Study Sediment Data Rpt - Appendix B - DUSRs.pdf
185K
Report.HW.442027.2013-02-01.Southern FS Study Sediment Data Rpt - Appendix C - Sediment Toxicity Data.pdf
47M
Report.HW.442027.2013-02-01.Southern FS Study Sediment Data Rpt.pdf
6.7M
Report.HW.442027.2014-04-28.Hudson River OU 02 Feasibility Study.pdf
51M
Report.HW.442027.2014-05-07.Const.Completion Report for OU1.pdf
311M
Report.HW.442027.2018-09-10.revised Final 100 percent Remedial Design Specs and Drawings - OU2.pdf
51M
Report.HW.442027.2019-07-29.7-29 OU2 Rensselaer Noise Monitoring Report.pdf
208K
Report.HW.442027.2019-12-13.OU1 - 2019 PRR.pdf
17M
Report.HW.442027.2023-11-29.CCR_OU2_FINAL_Appendix E.2.pdf
563M
ROD.HW.442027.2003-09-11.BASF OU 01 Record of Decision - signed.pdf
880K
ROD.HW.442027.2003-09-11.OU1 basf_manufacturing_plant.pdf
154K
ROD.HW.442027.2003-09-11.OU1 BASF_ROD_Figures.pdf
2.9M
ROD.HW.442027.2016-03-29.basf OU 02 record of decision.pdf
1.4M
Work Plan.HW.442027.2004-04-23.Revised_Work_Plan_for_OU2.pdf
4.9M
Work Plan.HW.442027.2004-06-01.OU1 in-situ-treatment-lagoon-area-groundwater.RD-RA.pdf
7.5M
Work Plan.HW.442027.2005-09-01.Hudson-River_OU2_Investigation.pdf
23M
Work Plan.HW.442027.2007-08-01.Hudson-River_OU2_Investigation - Supplemental Investigation.pdf
8.1M
Work Plan.HW.442027.2008-06-12.OU1 RA_for_Lagoon_Area.pdf
1.1M
Work Plan.HW.442027.2008-08-12.OU1 Limited_Soil_Investigation-Lagoon_Area.Roux.pdf
551K
Work Plan.HW.442027.2010-03-19.OU1 BASF_Building-Demolition_and_Materials_ManagementPlan.pdf
5.8M
Work Plan.HW.442027.2010-09-14.OU1 soil_vapor_monit_plan.ROUX.pdf
131K
Work Plan.HW.442027.2011-06-15.OU2-Southern_FS_SamplingWP_for_DEC.pdf
458K
Work Plan.HW.442027.2011-09-15.OU2-PCB_SamplingWP-Final_for_EPA.pdf
4.4M
Work Plan.HW.442027.2011-10-24.boat_ramp_sampling_plan.ROUX.pdf
248K
Work Plan.HW.442027.2012-10-11.second_BoatRampExcavationWP.pdf
263K
Work Plan.HW.442027.2013-01-14.Natural_Resource_Damages_WP.AECOM.pdf
4.7M
Work Plan.HW.442027.2013-11-01.OU2_additional_PCB_Sampling_for_FS.AECOM.pdf
529K
Work Plan.HW.442027.2014-02-27.Final_Natural_Resource_Restoration_WP.pdf
4.7M
Work Plan.HW.442027.2016-08-31.OU 02 Pre-Design sampling in Hudson.pdf
1.8M
Work Plan.HW.442027.2017-11-06.revised Hudson River OU 02 RD-RA Work Plan - No Confidentiality Granted.pdf
5.1M
Work Plan.HW.442027.2018-04-19.revised Hudson River OU02 Upland Site Prep WP.pdf
2.3M
Work Plan.HW.442027.2019-07-09.OU2 Revised Surface Water Remedial Action Monitoring Plan (Appendix G, 2019, Final).pdf
1.6M
Work Plan.HW.442027.2019-12-05.OU1 - draft revised interim smp 2019.pdf
124M
Work Plan.HW.442027.2020-06-11.workplan hw442027 2020-06-11 DEC to AECOM - Approved Changes to SAV Planting Procedures - OU2 Restoration.pdf
836K