Name
Size
Agreement.BCP.C203169.2023-12-15.Sol_on_Park.pdf
403K
Application.BCP.C203169.2022-03-07.Phase I Environmental Site Assessment.pdf
145M
Application.BCP.C203169.2023-03-24.Phase II Environmental Site Assessment Summary Report.pdf
11M
Application.BCP.C203169.2023-08-18.Complete Application.pdf
18M
Fact Sheet.BCP.C203169.2024-07-03.RIWP Fact Sheet (Spanish).pdf
811K
Fact Sheet.BCP.C203169.2024-07-03.RIWP Fact Sheet.pdf
971K
Fact Sheet.BCP.C203169.2026-05-13.RIR Fact Sheet (Spanish).pdf
684K
Fact Sheet.BCP.C203169.2026-05-13.RIR Fact Sheet.pdf
819K
Fact Sheet.BCP.C203169.2026-05-20.RAWP Fact Sheet (Spanish).pdf
1.2M
Fact Sheet.BCP.C203169.2026-05-20.RAWP Fact Sheet.pdf
1.2M
Report.BCP.C203169.2024-09-11.Monthly Report August 2024.pdf
146K
Report.BCP.C203169.2024-10-01.Daily Reports - September 2024.pdf
16M
Report.BCP.C203169.2024-10-14.Monthly Report September 2024.pdf
221K
Report.BCP.C203169.2024-11-18.Monthly Report October 2024.pdf
234K
Report.BCP.C203169.2024-12-16.Monthly Report November 2024.pdf
128K
Report.BCP.C203169.2025-01-14.Monthly Report December 2024.pdf
128K
Report.BCP.C203169.2025-02-11.Monthly Report January 2025.pdf
129K
Report.BCP.C203169.2025-03-10.Monthly Report February 2025.pdf
129K
Report.BCP.C203169.2025-04-11.Monthly Report March 2025.pdf
128K
Report.BCP.C203169.2025-05-12.Monthly Report April 2025.pdf
128K
Report.BCP.C203169.2025-06-13.Monthly Report May 2025.pdf
129K
Report.BCP.C203169.2025-07-10.Monthly Report June 2025.pdf
129K
Report.BCP.C203169.2025-08-20.Monthly Report July 2025.pdf
129K
Report.BCP.C203169.2025-09-11.Monthly Report August 2025.pdf
130K
Report.BCP.C203169.2025-10-17.Monthly Report September 2025.pdf
148K
Report.BCP.C203169.2025-11-19.Monthly Report October 2025.pdf
149K
Report.BCP.C203169.2025-12-15.Daily Reports - November 2025.pdf
3.2M
Report.BCP.C203169.2025-12-16.Monthly Report November 2025.pdf
149K
Report.BCP.C203169.2026-01-15.Daily Reports - December 2025.pdf
3.8M
Report.BCP.C203169.2026-01-15.Monthly Report December 2025.pdf
149K
Report.BCP.C203169.2026-02-10.Monthly Report January 2026.pdf
149K
Report.BCP.C203169.2026-03-13.Monthly Report February 2026.pdf
149K
Report.BCP.C203169.2026-04-03.Remedial Investigation Report - Appendix B.pdf
155M
Report.BCP.C203169.2026-04-03.Remedial Investigation Report - Appendix I (Part 1).pdf
1.3G
Report.BCP.C203169.2026-04-03.Remedial Investigation Report - Appendix I (Part 2).pdf
1.0G
Report.BCP.C203169.2026-04-03.Remedial Investigation Report.pdf
89M
Report.BCP.C203169.2026-04-10.Monthly Report March 2026.pdf
149K
Report.BCP.C203169.2026-05-15.Daily Reports - April 2026.pdf
2.6M
Report.BCP.C203169.2026-05-15.Monthly Report April 2026.pdf
149K
Work Plan.BCP.C203169.2024-05-08.Citizen Participation Plan (Public Version).pdf
723K
Work Plan.BCP.C203169.2024-08-20.RIWP.pdf
209M
Work Plan.BCP.C203169.2025-11-14.SRIWP.pdf
25M
Work Plan.BCP.C203169.2026-02-26.DRAFT RAWP - Appendix C.pdf
155M
Work Plan.BCP.C203169.2026-02-26.DRAFT RAWP - Appendix H (Part 1).pdf
1.3G
Work Plan.BCP.C203169.2026-02-26.DRAFT RAWP - Appendix H (Part 2).pdf
1.0G
Work Plan.BCP.C203169.2026-02-26.DRAFT RAWP - Appendix M.pdf
69M
Work Plan.BCP.C203169.2026-02-26.DRAFT RAWP.pdf
87M
Work Plan.BCP.C203169.2026-05-12.Revised Citizen Participation Plan (Public).pdf
591K